Hello all,
I would like to know if there is any possibility in AIMMS to limit/penalize via constraints/costs the amount of changeovers done by a machine per type of product and even take into account the capacity lost linked to these.
Example:
- Production Line A has the capability to produce products X, Y and Z
- Changing the production to another product has a big impact on capacity linked changeover time (several days) and should be avoided as much as possible
- In a month, there is a maximum of 1 changeover
How could I use AIMMS to model these constraints?
- Can the changeover impact on capacity be modelled (amount of days lost)?
- Can I set a penalty/cost in order to avoid changeovers as much as possible?
- Can I set a max of changeovers for a specific period?
Many thanks in advance for your comments!
Carlos